Signals Served #027 - The Backlog Has a Cap Table
Issue #027 of Signals Served - The Backlog Has a Cap Table. Week of September 1-7, 2026. 13 signals with a Founder Signal for each.
Signal of the Week. SB Energy's September 1 announcement that it had publicly filed a registration statement for a proposed listing. The backlog, customer and guarantee detail is in the S-1.
About $439B of backlog under binding contracts, roughly $430B of it in the data-centre segment, against 8.8 GW-IT of contracted capacity held by two customers: OpenAI, on twenty-year leases for about 8.0 GW-IT in Ohio, and SoftBank, which owns the company. Weighted average remaining term: 19.6 years.
The guarantor's side: the Ohio campus hosts Nvidia compute exclusively. As the issue reads it, the guarantee covers the initial 4.25 GW-IT phase, and Nvidia may elect, but is not obliged, to guarantee the remaining 3.78 GW-IT.
September 3: an initial $3.5B compute commitment with stated intent to exceed $6B, deployment targeted for the second half of 2027, and a strategic investment that makes Nscale a Figure shareholder and its preferred compute provider. Commitment and equity were announced together.
September 3: a roughly $13B, five-year cloud agreement. Bloomberg's sourcing says the contract helped attract interest in Crusoe's raise the same week.
More than $3B at a valuation of roughly $30B, co-led by Atreides Management and Valor Equity Partners with Mubadala Capital participating, reported the same day as the Jane Street contract.
September 3: a previously unreported $1.5B round valuing Fluidstack above $18B, led by Jane Street, which Forbes also identifies as a customer. No closing date given; Bloomberg reported talks at the same valuation in April, so this may be that process closing.
Definitive agreement executed September 2: about $11.9B payable to shareholders plus up to roughly $1B in employee equity retention, expected to close in the first half of 2027, subject to conditions. Nvidia says its compute will not be required to build on or deploy through Hugging Face.
Nvidia's filing for the agreement executed September 2 and announced September 3; closing expected in the first half of 2027, subject to conditions.
September 4, citing a source: about $1.5B of convertible notes led by Third Point and about $2B more it aims to secure from Nvidia, with Goldman Sachs advising, ahead of a planned US listing. Participation and final size are unsettled.
From investor documents: a contracted backlog above $100B, up from about $51B a month earlier. Not a filing: Nscale has not said who owes it, on what terms, or with whose credit behind it.
Cited for Nscale's last established mark: $14.6B at its March Series C.
September 4: led by Andreessen Horowitz, with Sapphire Ventures, M12, Arm, Menlo Ventures and Factory. The release says Gimlet has secured billions in contracted revenue for Gimlet Cloud; that is the company's own, unaudited figure.
September 3: a definitive agreement to acquire EPC Power, a power-conversion manufacturer serving AI data centres and grid applications, for $4.4B. Expected to close in the fourth quarter.
September 2: Uplift Ventures, backed by Jungheinrich, launched a €100M fund for deeptech and industrial technology.
September 1: $450M of new equity, all from existing institutional shareholders.
September 1: the round is described as about $1B at a $21B valuation. Reported as prospective; neither the company nor the lead investor has confirmed a close.
About $100M at roughly $450M-$470M (accounts differ), more than halving its prior mark and far below the $1.5B it carried in 2021. Neo Wealth reportedly led, with Kado Global and Moore Strategic Ventures, as Slice becomes a small finance bank.
A second report, at the low end of the range; the issue gives $450M-$470M because accounts differ.
September 3: Accel's seed into Atira, an AI orchestration layer for industrial sales engineering: a named buyer and a named job.