title: "Step 6: Membrane Cure and Hold Point Before Next Layer"
url: https://stacklist.com/card/ab0e4802-1043-4f38-a5fb-1ce2d65decc4
stack: https://stacklist.com/c/business/stack/2d67154e-83fe-4367-99db-e7e4088ce2f9
summary: "Step 6 establishes a mandatory hold point requiring full membrane cure and visual inspection before installing drainage mats or protection boards. Cure requires minimum 24 hours at 70°F and 50% humidity, with extended times for lower temperatures, and includes verification through visual inspection, touch test, and probe test."
tags: "membrane-cure, hold-point, quality-control, roofing, inspection, construction-protocol, cure-verification"
key_entities: "membrane cure (concept), hold point (concept), visual inspection (concept), FM ELEVATION repair protocol (concept), adhesion failures (concept), drainage mat (concept)"
classification: "checklist"
content_hash: "sha256:4c9590079c95cf40391911ac6379d17c79608ea2520990525bd6f16a668fb000"
acp_version: "0.2"
token_counts_approximate: 461
visibility: public
agent_accessible: true
status: "final"
---

# Step 6: Membrane Cure and Hold Point Before Next Layer

Step 6: Membrane Cure and Hold Point Before
Next Layer 
Overview 
This is a mandatory hold point. No drainage mat, protection board, or topping may be installed until the
membrane has fully cured and a visual inspection is completed. Placing weight or traffic on an uncured
membrane causes adhesion failures and punctures. 
Cure Requirements 
Minimum cure time: 24 hours at 70F and 50% relative humidity 
At lower temperatures or higher humidity: Extend cure time. At 50F, allow minimum 48 hours.
Below 40F, membrane will not cure. Stop work. 
No rain or standing water during the cure window. If rain occurs, inspect the membrane after it
dries and before proceeding. 
No foot traffic on the cured membrane except for the inspector. Use plywood walk boards if access
is needed. 
Cure Verification 
Visual: membrane surface should appear uniform in color and sheen. Dull or chalky spots may
indicate incomplete cure or primer issues. 
Touch test: membrane should feel firm and non-tacky 
Probe test: press a blunt tool (pen cap) into the membrane surface. The surface should not indent
permanently. 
Cure Log 
Item Value 
Membrane installation date 
Cure start time 
Ambient temp during cure 
8/8/26, 12:46 AM Step 6: Membrane Cure and Hold Point Before Next Layer 
https://md2pdf.netlify.app 1/2 

Item Value 
Relative humidity during cure 
Any rain events? Y / N 
Cure end time 
Visual inspection result Pass / Fail 
Inspector name 
Sign-off to proceed ______________ Date: ______________ 
If Inspection Fails 
Identify and mark all defects (lifts, fishmouths, bubbles, thin spots) 
Repair per FM ELEVATION repair protocol before proceeding 
Re-inspect and log after repairs 
Do not proceed to Step 7 until this hold point is signed off 