title: "Check 5: Scupper Sequencing and Membrane Integration"
url: https://stacklist.com/card/8ce51679-bc93-4b03-bf8a-e241d6599b1b
stack: https://stacklist.com/c/business/stack/8b50c285-c1e7-42de-ac4c-343659a54e54
summary: "Check 5 is an inspection checklist for scupper sequencing and membrane integration on roofing projects, requiring verification of proper scupper pre-set, membrane lap and adhesion, and drainage clearance before proceeding to flood testing. All items must be signed off by an inspector to ensure water drainage functions correctly and no membrane material blocks the scupper opening."
tags: "scupper, membrane-integration, drainage, roofing-inspection, quality-control, construction-checklist, hold-point"
key_entities: "scupper-membrane-integration (concept), membrane-flange-lap (concept), drainage-path (concept), flood-test (concept), hold-point-inspection (concept)"
classification: "checklist"
content_hash: "sha256:e157762f9f62bcf7b699642781b5684546c52efeb70b98b559b1d347bec16c97"
acp_version: "0.2"
token_counts_approximate: 466
visibility: public
agent_accessible: true
status: "final"
---

# Check 5: Scupper Sequencing and Membrane Integration

Check 5: Scupper Sequencing and Membrane
Integration 
Hold Point: Scupper-membrane integration must be inspected before drainage mat is placed. 
Scupper Pre-Set (before membrane) 
[ ] Scupper box is set and fastened before any membrane is installed 
[ ] Scupper elevation matches the finished deck slope: no low spots at scupper perimeter 
[ ] Flange is flat and flush with the substrate: no rocking or lifting 
[ ] Scupper opening is the correct size for the drainage area it serves 
[ ] Scupper is at the correct height to receive the membrane flange and still drain freely 
Membrane Integration 
[ ] Membrane field layer laps over the scupper flange a minimum of 3 in. 
[ ] Membrane is fully adhered over the flange: no lifting or bridging at the flange perimeter 
[ ] Membrane is cut cleanly at the scupper throat: no material blocking the opening 
[ ] Membrane shingles into the scupper opening: upper layer over lower layer, water runs with the
lap 
[ ] No exposed flange: membrane covers the full flange on all four sides 
Throat and Outlet 
[ ] Scupper throat is clear: no membrane scraps, debris, or tools blocking drainage 
[ ] Scupper outlet is free: confirms drainage path is open to the exterior 
[ ] Scupper leader or downspout connection is confirmed before flood test 
Inspector Sign-Off 
Item Pass Inspector Date 
Scupper pre-set before membrane [ ] __________ __________ 
8/8/26, 12:58 AM Check 5: Scupper Sequencing and Membrane Integration 
https://md2pdf.netlify.app 1/2 

Item Pass Inspector Date 
Flange lap 3 in. min, fully adhered [ ] __________ __________ 
Membrane shingles into opening [ ] __________ __________ 
Throat and outlet clear [ ] __________ __________ 
Do not proceed to flood test until all scupper checks are signed off. 