title: "Section 6: Pre-Bid Coordination Checklist for FM Waterproofing"
url: https://stacklist.com/card/6ccabeee-c934-490b-95d1-c5398b583750
stack: https://stacklist.com/c/technology/stack/ccc8a635-1426-4960-958d-568d07671c5e
summary: "Section 6 provides a pre-bid coordination checklist for FM waterproofing projects, outlining requirements for general contractors and architects to confirm before soliciting bids. The checklist includes bid package verification, scope confirmation assignments, and a pre-installation meeting agenda to ensure proper specification, material selection, and project sequencing."
tags: "waterproofing, pre-bid, checklist, construction, coordination, fm-systems, division-07"
key_entities: "FM SP1 (technology), S60 membrane (technology), DM2 drainage mat (technology), TTP (technology), TTP-6 pocket (technology), flood test (concept), FM-certified applicator (concept), FM warranty (concept), Division 07 Waterproofing (concept), Division 05 Structural (concept)"
classification: "checklist"
content_hash: "sha256:b448ce784f2a18bdd65319fead24d9716b2f31f0a5c8a4e50c0ddd1917f12dae"
acp_version: "0.2"
token_counts_approximate: 523
visibility: public
agent_accessible: true
status: "final"
---

# Section 6: Pre-Bid Coordination Checklist for FM Waterproofing

Section 6: Pre-Bid Coordination Checklist for FM
Waterproofing 
What the GC and architect need to confirm before bids go out. 
Bid Package Checklist 
[ ] Division 07 spec includes FM SP1, S60, and DM2 by name 
[ ] TTP numbers referenced in spec and drawing set 
[ ] Flood test requirement in Part 3 of Division 07 
[ ] FM 10-year warranty requirement in Part 1 
[ ] FM-certified applicator qualification required in Part 1 submittals 
[ ] Railing embed method (TTP-6 pocket) shown on waterproofing plan sheet 
[ ] Division 05 cross-reference note added to railing spec 
[ ] TTP detail drawings bound in the drawing set 
[ ] Flood test drawing note on waterproofing plan sheet 
Scope Confirmation Table 
Item Scope Assigned To 
SP1 primer Division 07 Waterproofing applicator 
S60 membrane Division 07 Waterproofing applicator 
DM2 drainage mat Division 07 Waterproofing applicator 
Transition detailing (TTP) Division 07 Waterproofing applicator 
Railing pocket waterproofing (TTP-6) Division 07 Waterproofing applicator 
Railing post setting Division 05 Structural/railing sub 
Flood test Division 07 Waterproofing applicator 
Flood test documentation Division 07 Waterproofing applicator 
8/8/26, 1:10 AM Section 6: Pre-Bid Coordination Checklist for FM Waterproofing 
https://md2pdf.netlify.app 1/2 

Item Scope Assigned To 
Protection board Division 07 Waterproofing applicator 
Concrete topping Division 03 Concrete sub 
FM warranty submittal Division 07 Waterproofing applicator (via GC) 
Pre-Installation Meeting Agenda 
1. Confirm FM-certified applicator is on site crew 
2. Review TTP details applicable to this project 
3. Confirm railing pocket locations and coordinate with Division 05 sub 
4. Establish flood test date and notification procedure 
5. Confirm submittal package requirements for FM warranty 
6. Review sequencing: primer, membrane, flood test, drainage mat, protection board, topping 
7. Confirm inspection hold points and who signs off at each stage 