title: "Check 9: Protection Board Coverage Before Topping"
url: https://stacklist.com/card/6c5bac4d-170f-48f1-bb06-4b8e5af7bec0
stack: https://stacklist.com/c/business/stack/8b50c285-c1e7-42de-ac4c-343659a54e54
summary: "Check 9 is a critical hold-point inspection verifying that protection board completely covers the drainage mat with no gaps, damage, or exposed materials before concrete or tile topping is applied. The checklist ensures proper board condition, clearance at drains/scuppers/walls/penetrations, and requires PM approval before any topping work begins."
tags: "protection-board, quality-assurance, construction-checklist, roofing-inspection, drainage-mat, hold-point, pre-topping"
key_entities: "protection board coverage (concept), drainage mat (concept), hold point inspection (concept), drain clamping ring (concept), scupper throat clearance (concept), membrane termination (concept), PM sign-off (concept)"
classification: "checklist"
content_hash: "sha256:2f5593331a6dca8c95b013513c58ff8c8262477f22bd610dabcb1be18e5de890"
acp_version: "0.2"
token_counts_approximate: 523
visibility: public
agent_accessible: true
status: "final"
---

# Check 9: Protection Board Coverage Before Topping

Check 9: Protection Board Coverage Before
Topping 
Hold Point: This is the last visual inspection before the assembly is permanently closed. Do not place
concrete or tile topping until this check passes. 
Coverage 
[ ] Protection board covers 100% of the drainage mat area: no gaps or missing sections 
[ ] Boards are butted tightly: no open joints wider than 1/4 in. 
[ ] No sections of drainage mat or membrane are left exposed before topping 
Board Condition 
[ ] Boards are undamaged: no cracks, breaks, or soft spots 
[ ] No debris or tools are trapped under the board layer 
[ ] Boards are lying flat: no rocking, bowing, or raised edges 
Clearance at Drains and Scuppers 
[ ] Protection board is cut cleanly around the drain clamping ring: ring is not covered 
[ ] Drain ring is accessible for final inspection before topping 
[ ] Protection board terminates cleanly at scupper throats: no material blocking opening 
[ ] Scupper throat clearance is confirmed: drainage path is unobstructed 
Clearance at Walls and Penetrations 
[ ] Protection board terminates 1/2 in. from all walls and curbs: no compression against the
membrane termination 
[ ] All penetrations are clear: no board material bridging or covering the membrane flashing at pipes
or posts 
PM Approval Before Topping 
8/8/26, 12:59 AM Check 9: Protection Board Coverage Before Topping 
https://md2pdf.netlify.app 1/2 

[ ] PM or GC representative has walked the full deck area 
[ ] All items above are signed off before any concrete or tile topping begins 
[ ] No topping trucks or tile setters on site until PM sign-off is complete 
Inspector Sign-Off 
Item Pass Inspector Date 
100% board coverage, no gaps [ ] __________ __________ 
Board condition: undamaged, flat [ ] __________ __________ 
Drain and scupper clearance [ ] __________ __________ 
Wall and penetration clearance [ ] __________ __________ 
PM walk and sign-off [ ] __________ __________ 
Assembly is now cleared to receive concrete or tile topping. 