title: "Check 2: SP1 Primer Application and Coverage"
url: https://stacklist.com/card/5cf8f491-42c0-40f8-980c-ea671ba960ea
stack: https://stacklist.com/c/business/stack/8b50c285-c1e7-42de-ac4c-343659a54e54
summary: "Check 2 is a quality control checklist for SP1 primer application and coverage verification before S60 membrane installation. It specifies pre-application conditions, application standards, flash-off requirements, and documentation procedures to ensure proper primer curing and coverage."
tags: "primer-application, sp1, membrane-installation, quality-control, construction-checklist, flash-off, substrate-preparation"
key_entities: "SP1 primer (technology), S60 membrane (technology), flash-off (concept), substrate temperature (concept), coverage rate (concept)"
classification: "checklist"
content_hash: "sha256:178446daee99ba4eba8617b6b0f02b9574afe01f056dab550689ccd2e8715be4"
acp_version: "0.2"
token_counts_approximate: 487
visibility: public
agent_accessible: true
status: "final"
---

# Check 2: SP1 Primer Application and Coverage

Check 2: SP1 Primer Application and Coverage 
Hold Point: Do not apply S60 membrane until primer has fully flashed off and cured. 
Pre-Application Conditions 
[ ] Ambient temperature is above 40°F (4°C) and rising 
[ ] Substrate temperature is above 40°F 
[ ] No rain or dew expected during application or flash-off window 
[ ] Substrate passes Check 1: dry, clean, cured 
[ ] Wind speed is acceptable: no conditions that will cause uneven application or premature skinning 
Application 
[ ] SP1 is applied at the correct coverage rate (confirm with FM spec sheet for substrate type) 
[ ] Primer is applied in a uniform, continuous film: no holidays, pinholes, or missed areas 
[ ] All edges, coves, and transitions are primed, not just the field 
[ ] Vertical surfaces to receive membrane are primed to the full termination height 
[ ] No puddling or excess primer in low spots 
Flash-Off and Cure 
[ ] Primer has fully flashed off: tacky to the touch but not transferring to glove 
[ ] Flash-off time observed per FM spec (typically 30 to 60 min at 70°F, longer at lower temps) 
[ ] Membrane application begins within the open time window: not too early, not too late 
[ ] No rain or foot traffic on primed surface before membrane is applied 
Documentation Log 
Item Value Inspector Date/Time 
Ambient temp at application ________°F __________ __________ 
Substrate temp at application ________°F __________ __________ 
8/8/26, 12:56 AM Check 2: SP1 Primer Application and Coverage 
https://md2pdf.netlify.app 1/2 

Item Value Inspector Date/Time 
Coverage rate used ________ sq ft/gal __________ __________ 
Flash-off start time __________ __________ __________ 
Flash-off confirmed (tacky) [ ] __________ __________ 
Membrane application start __________ __________ __________ 
Do not proceed to S60 membrane until flash-off is confirmed and logged. 