title: "Check 4: Transitions, Penetrations, and Wall Terminations"
url: https://stacklist.com/card/1df2368f-a775-4400-a1af-18b27a573c67
stack: https://stacklist.com/c/business/stack/8b50c285-c1e7-42de-ac4c-343659a54e54
summary: "Check 4 is a comprehensive inspection checklist for roof membrane transitions, penetrations, and wall terminations that must be completed before flood testing. It covers wall laps, membrane adhesion, penetration flashing, cove details, and through-the-parapet pockets with specific requirements and inspector sign-off procedures."
tags: "roof-inspection, membrane-installation, penetrations, wall-terminations, checklist, quality-assurance, flood-test"
key_entities: "membrane-laps (concept), penetration-flashing (concept), wall-terminations (concept), cove-fillet (concept), through-the-parapet-pockets (concept), flood-test (concept)"
classification: "checklist"
content_hash: "sha256:41f575e89ee7ea3dd2c512d943a7fb13502eed99d4f9bbf4e05d84186fa1192f"
acp_version: "0.2"
token_counts_approximate: 523
visibility: public
agent_accessible: true
status: "final"
---

# Check 4: Transitions, Penetrations, and Wall Terminations

Check 4: Transitions, Penetrations, and Wall
Terminations 
Hold Point: All transitions and penetrations must be fully detailed before flood test. 
Wall Terminations 
[ ] Membrane laps a minimum of 6 in. up all vertical surfaces: walls, curbs, door thresholds 
[ ] Membrane is fully adhered to the vertical substrate: no tenting or gaps at the cove 
[ ] Top edge of membrane is terminated with a bar, caulk bead, or counter-flashing per FM detail 
[ ] No exposed membrane edges at any wall or curb termination 
[ ] Threshold details are continuous: no gaps at door frame corners 
Penetrations (pipes, conduit, posts) 
[ ] All penetrations are pre-sleeved or have a formed flashing before membrane installation 
[ ] Membrane wraps a minimum of 6 in. up each penetration sleeve 
[ ] No membrane is cut or notched around a penetration without a formed patch 
[ ] Caulk or sealant is applied at the membrane-to-sleeve termination per FM detail 
[ ] All penetrations are within 12 in. of a drain or scupper (confirm with FM detail if not) 
Coves and Inside Corners 
[ ] Cove fillet or cant strip is installed at all wall-to-deck transitions before membrane 
[ ] Membrane bridges the cove continuously: no bridging or air pockets at inside corners 
[ ] Outside corners are folded and adhered: no open miters 
TTP (Through-the-Parapet) Pockets 
[ ] TTP pockets are fully formed before membrane installation 
[ ] Membrane laps into the pocket per FM detail: no short laps at the pocket opening 
[ ] Pocket is sealed at the exterior face before flood test 
8/8/26, 12:57 AM Check 4: Transitions, Penetrations, and Wall Terminations 
https://md2pdf.netlify.app 1/2 

Inspector Sign-Off 
Item Pass Inspector Date 
Wall terminations 6 in. min [ ] __________ __________ 
All penetrations flashed [ ] __________ __________ 
Coves and corners continuous [ ] __________ __________ 
TTP pockets sealed [ ] __________ __________ 
Do not proceed to flood test until all transition checks are signed off. 